Which step must be performed immediately before applying a sealant?

  1. Fluoride varnish application
  2. Tooth etching with phosphoric acid
  3. Polishing with coarse paste
  4. Checking occlusion
Show answer and explanation

Correct answer: Tooth etching with phosphoric acid

Etching creates microscopic porosity in enamel to allow sealant retention. It is a critical bonding step.