Quality Assurance in Dental Practice · CDA

Which activity is part of a quality assurance program?

  1. Ignoring patient complaints
  2. Performing routine equipment maintenance
  3. Skipping sterilization verification tests
  4. Reducing staff communication
Show answer and explanation

Correct answer: Performing routine equipment maintenance

Regular equipment maintenance ensures reliable performance and reduces errors. It supports safe and effective care.

Difficulty: Medium Question 2 of 20

Practice all 20 Quality Assurance in Dental Practice questions